UPS service
A preventive maintenance visit checks the parts of a UPS that wear out before they cause an outage: batteries, cooling fans, capacitors, air filters and power connections. We schedule one or two visits a year, test the system under its real load, and leave a written report with readings and recommendations. Visits run across Canada, with same-day dispatch in Montreal, Quebec City, Toronto and Ottawa.

The full checklist is in our three-phase UPS preventive maintenance guide.
Manufacturers publish service lives for the parts that age. As an example, the user manual of the Liebert EXM2 (100 to 250 kVA) gives these figures:
| Part | Estimated life | Proposed replacement |
|---|---|---|
| Fan | Not less than 7 years | 6 years |
| Bus capacitor | Not less than 7 years | 6 years |
| VRLA battery (5-year design life) | 5 years | 3 to 4 years |
Other families publish their own intervals, and a hot room shortens all of them. We track every part's age in the report so replacements can be budgeted instead of discovered.
Once a year is the minimum for any UPS protecting a critical load; twice a year is better for large systems and for sites with a warm or dusty room. Vertiv's reliability study found that units maintained twice a year had a mean time between failures 23 times higher than units with no maintenance, and concluded that two or more visits a year substantially increase reliability.
Some checks are worth doing between visits. Eaton recommends a thermal scan every three months and a full mechanical review of the UPS and battery cabinets each year, and says air filters should be inspected every month.
Plans are written as maintenance contracts with the response times and parts terms spelled out.
The checklist behind these visits is laid out item by item in this description of a preventive maintenance program for UPS systems. Smaller rack and tower fleets are also covered by UPS maintenance plans for single-phase units.
Every visit ends with a written report: battery readings per block or cell, thermal images of anything abnormal, the event log summary, parts replaced, the age of each wear part and a prioritized list of recommendations. Readings are compared with the previous visit so trends show up early. Facility managers use it for budgets; auditors use it as maintenance evidence.
At least once a year, and twice a year for large three-phase systems or warm, dusty rooms. Vertiv's data shows a mean time between failures 23 times higher with two visits a year than with none.
Usually not. Inspection, thermal scanning and battery testing are done with the load running. Tests that need a transfer to bypass or a shutdown are scheduled with you in advance.
Air filters are cleaned or replaced on the spot. Fans, capacitors and batteries are replaced when they reach the manufacturer's interval or test poorly, after you approve the quote.
Warranty work stays with the manufacturer. Many owners still add their own inspections, or hand maintenance over to us when the warranty ends.
Yes. Rack and tower units get a shorter visit focused on the battery, fans and event log, often grouped with the three-phase systems on the same site.
We reply with a quote within 4 business hours. Planned visits are booked around your operations; emergencies are dispatched the same day in Montreal, Quebec City, Toronto and Ottawa, and within 24 to 48 hours elsewhere.
Sources, checked October 4, 2026: