Three-phase UPS commissioning: what each manufacturer includes

Commissioning a three-phase UPS is the on-site start-up and test sequence that proves the installed system before it carries the load. For many current models the manufacturer ties start-up to its own service: Schneider includes a 5x8 start-up in the part numbers of the Galaxy VS, VL, VX and Easy UPS models we list, and Eaton includes start-up on the 93PM and 9395 family and defines it as work by an Eaton engineer or agent.

Technician on a ladder running power conduit above UPS panels in an equipment room

Start-up and built-in test features by model

ModelStart-up and on-site testingStatusSource
APC Galaxy VS
GVSUPS20KFS (20 kW, 208 V) and GVSUPS100KGS (100 kW, 480 V)
Start-up 5x8 included in the part (GVSUPS20KFS, GVSUPS100KGS)CurrentSchneider Electric Canada, GVSUPS20KFS; Schneider Electric Canada, GVSUPS100KGS
APC Galaxy VX
GVX500K750HS (500 kVA scalable to 750 kVA, 400 V)
Start-up 5x8 included in the partCurrentSchneider Electric Canada, GVX500K750HS
APC Galaxy VL
GVL200K500DS (200 kW scalable to 500 kW, 400/480 V)
Start-up 5x8 included in the partCurrentSchneider Electric Canada, GVL200K500DS
APC Easy UPS 3S
E3SUPS20KFBS (20 kVA, 208 V, internal batteries)
Start-up 5x8 included in the partCurrentSchneider Electric Canada, E3SUPS20KFBS
APC Easy UPS 3M
E3MUPS120KHS (120 kVA, 400 V)
Start-up 5x8 included in the partCurrentSchneider Electric, E3MUPS120KHS
Eaton 93PM
93PM 208V (North America)
Startup included; done by an Eaton Customer Service Engineer or agent; warranty runs from startupCurrentEaton, 9315, 93PM and 9395 startup, warranty and support overview
Eaton Power Xpert 9395P
Power Xpert 9395P, 200 to 1,200 kVA
Startup included (9395 family); battery start standardCurrentEaton, 9315, 93PM and 9395 startup, warranty and support overview; Eaton, Power Xpert 9395P page
Eaton 9395XC
9395XC, 1,125 to 2,250 kW, 480 V 3-wire
Battery startup and soft start standard; startup included (9395 family)CurrentEaton, 9395XC UPS page; Eaton, 9315, 93PM and 9395 startup, warranty and support overview
Eaton 9395XR
9395XR, 1,500 kW
Cold start; rectifier soft-start ramp-up for generatorsCurrentEaton, 9395XR UPS page
Vertiv Liebert EXL S1
Liebert EXL S1 (brochure for 625 to 800 kVA)
Power walk-in 1 to 300 s; safe capacity mode tests UPS load and battery discharge without an external load bankCurrentVertiv, Liebert EXL S1 625-800 kVA brochure; Vertiv, Liebert EXL S1 page
Vertiv Trinergy (newer range)
Vertiv Trinergy, the newer range that follows the Trinergy Cube (brochure SL-71331)
Walk-in soft start 15 s (1 to 90 s selectable)Partly discontinuedVertiv, Trinergy UPS brochure SL-71331
Toshiba G9000
G9000, 100 to 1,050 kVA
Generator friendly; accepts 0 to 100% load stepsCurrentToshiba International, G9000 series
Mitsubishi Electric 9900B
9900B, 300, 500 and 750 kVA at 480 V
1.1:1 generator compatibilityCurrentMitsubishi Electric, 9900B UPS
Mitsubishi Electric 9900AEGIS
9900AEGIS, 80 to 225 kVA at 480 V
1.1:1 generator sizingCurrentMitsubishi Electric, 9900AEGIS UPS
Delta Modulon DPH
DPH-300K, DPH-500K, DPH-600K (400 V)
Battery startCurrentDelta, DPH 50-600 kW specifications

Sources, checked October 3, 2026: values as each manufacturer publishes them for the model shown; “Not stated” means the page we read does not give the value.

Start-up and the warranty clock

Eaton's terms show why start-up timing matters. Outside the United States, the parts warranty on the 93PM and the 9395 family runs 12 months from start-up or 18 months from shipment, whichever comes first, and Eaton defines start-up as work by an Eaton Customer Service Engineer or agent. A unit that waits on site for months before start-up uses up warranty. Eaton also publishes a start-up checklist to complete before the visit.

Schneider's 5x8

The "Start-up 5x8" in Schneider part numbers is a start-up visit scheduled in weekday business hours. Schneider sells an upgrade from 5x8 to 7x24 scheduling for sites that need a night or weekend start-up.

Features that make the tests easier

Some built-in features change what a commissioning day needs. Vertiv's safe capacity mode on the Liebert EXL S1 tests UPS load and battery discharge without an external load bank; on models without that mode, the commissioning plan should include load bank testing of a UPS and its batteries before the unit carries the critical load. Walk-in timers set how fast the rectifier picks up load from a generator: 1 to 300 seconds on the EXL S1 and 15 seconds (1 to 90 selectable) on the Trinergy. Eaton lists battery start as standard on the 9395P and 9395XC and cold start on the 9395XR, and Delta lists battery start on the DPH.

What a start-up record should hold

Keep the settings the tests depend on with the start-up report: the walk-in time, the bypass voltage window (plus or minus 10% on the Galaxy VS; 10 to 20% upper and 10 to 40% lower on the Liebert APM2), the parallel configuration and the firmware revision. They are the first things checked when a transfer or a generator test does not behave as expected.

Installation and start-up can be booked through UPS installation and consulting service, and the start-up record becomes the baseline for preventive maintenance visits.

Frequently asked questions

Is start-up included with an APC Galaxy VS?

The part numbers we list, such as GVSUPS20KFS and GVSUPS100KGS, include "Start-up 5x8" in their Schneider descriptions.

Who has to start up an Eaton 93PM?

Eaton includes start-up and defines it as work by an Eaton Customer Service Engineer or agent; the warranty is counted from start-up.

Can the Liebert EXL S1 be load-tested without a load bank?

Vertiv's safe capacity mode tests UPS load and battery discharge without an external load bank.

How long is the Eaton warranty on a 9395 outside the US?

Eaton lists parts coverage of 12 months from start-up or 18 months from shipment, whichever comes first.

Related guides and systems

Request a system quote

Tell us the application and we reply within 4 business hours with the sizing, the right system, the installation and a written quote. Three-phase installs usually need a licensed electrician, so let us know if you have one.

Do you have your own electrician?
Yearly preventive maintenance?

Or email info@threephaseups.ca · 1 (438) 881-3363

Brand names are trademarks of their owners and are used only to identify the equipment we service. We are not the manufacturer and are not affiliated with it.